Power Supply Upgrade
Waste Water Treatment Works, West Devon
This project required the electrical design and installation of an upgraded power supply system to allow for the new solar PV system to be installed by our client’s external contractors. Work undertaken included:
Site management and welfare arrangements.
Civils installation of new cable ducts and kiosk plinths.
New kiosks to allow for new distribution boards and building services.
Electrical design and installation of new SWA cabling and power distribution equipment.
Site shutdown to allow for the new mains distribution board to be connected to the National Grid incoming power supply.
Installation of free issue export limitation equipment and commissioning.
This project was handed over to our client with all close-down documentation, ready for the new solar array to be energised.